Elizabethtown Gas is upgrading natural gas infrastructure in Perth Amboy, affecting the following streets: Alpine Street, Amboy Avenue, Boggs Street, Chester Street, Francis Street, Grove Street, Keene Street, Myrtle Street, and Spring Street.
Main installation – 11/6/24-12/5/24
Service renewals – 1/2/25 – 3/7/25
Main retirement – 3/10/25-3/17/25
Once all work is completed – 90 day settlement period and project will be paved.
Inclement weather could alter schedule
This project includes replacing aging gas mains with durable plastic pipe and relocating gas meters from inside homes and businesses to the outside for enhanced safety and reliability.
Proyecto de Reemplazo de Tuberías en Perth Amboy
Elizabethtown Gas está mejorando la infraestructura de gas natural en Perth Amboy, afectando las siguientes calles: Alpine Street, Amboy Avenue, Boggs Street, Chester Street, Francis Street, Grove Street, Keene Street, Myrtle Street y Spring Street.
Instalación principal – 11/6/24-12/5/24
Renovaciones de servicio – 1/2/25 – 3/7/25
Jubilación principal– 3/10/25-3/17/25
Una vez que todo el trabajo esté completado, habrá un período de liquidación de 90 días y el proyecto será pavimentado.
El proyecto incluye reemplazar las tuberías principales de gas envejecidas por tuberías de plástico duradero y reubicar los medidores de gas del interior de las viviendas y negocios hacia el exterior para mayor seguridad y confiabilidad.