WHAT TO EXPECT WHEN ROAD WORK COMES TO YOUR STREET

 The City of Perth Amboy has several local infrastructure projects to begin the week of April 10, 2023.  The projects are:
1. Street milling and paving from the Elizabethtown Gas pipeline replacement
2. Utility Service Affiliate’s fire hydrant replacements
3. Urban Enterprise Zone’s Road Rehabilitation and Improvements 
This page serves as an advisory of what you should know including:

  • Business and Residential Notices
  • Street Access
  • Garbage and Recycling Pick-up Schedules
  • Weekly Updates
  • More Information

We encourage residents and businesses to ask questions throughout the projects, either by calling us at (732) 826-7121 or sending us an e-mail at mayorsoffice@perthamboynj.org or speaking with city field inspectors on the street.

QUÉ ESPERAR CUANDO EL TRABAJO DE CARRETERA LLEGUE A SU CALLE

La Ciudad de Perth Amboy ha iniciado una serie de proyectos callejeros locales que incluyen pavimentación de calles, reemplazo de hidrantes contra incendios y las aceras en las veredas y las rampas.  Esta página sirve como aviso de lo que debe saber, incluyendo:

  • Avisos de negocios y residenciales
  • Acceso a la calle
  • Programas de recogida de basura y reciclaje
  • Actualizaciones semanales
  • Más información

Animamos a los residentes y negocios a hacer preguntas durante todo los proyectos, ya sea llamándonos al (732) 826-7121 o enviándonos un correo electrónico a mayorsoffice-perthamboynj.org o hablando con los inspectores de la ciudad en la calle.

CLICK HERE FOR THE LIST OF STREET CLOSURES

STREET ACCESS
During these construction projects, there is limited street access, and alternate routes are encouraged for those who do not live on the street. The contractor often places temporary “No Parking” signs on one or both sides of the street to ensure enough room for construction operations and vehicle access.  If your street is part of the milling and paving project (i.e., Elizabethtown Gas), the pavement will be replaced on one side at a time, allowing the street to remain open for traffic throughout construction. Parking on the street may be temporarily prohibited.  Streets will be open at night.

ACCESO A LA CALLE

Hay acceso limitado a la calle durante estos proyectos de construcción, y se recomiendan rutas alternativas para aquellos que no viven en la calle. El contratista a menudo coloca letreros temporales de "No estacionar" en uno o ambos lados de la calle para asegurarse de que haya suficiente espacio para las operaciones de construcción y el acceso de vehículos.
Si su calle es parte del proyecto de fresado y pavimentación (es decir, Elizabethtown Gas), el pavimento se reemplazará en un lado de la calle a la vez para permitir que la calle permanezca abierta al tráfico durante la construcción. El estacionamiento en la calle puede estar prohibido temporalmente. Las calles estarán abiertas por la noche.

CLICK HERE FOR THE LIST OF STREET CLOSURES

NOTICES OF WORK PROJECTS
All residents and  business owners with property abutting a road project will receive an informational letter before the street paving begins. It is important to read and save this letter for reference in the future.

Click HERE for the information letter in English and Spanish from ELIZABETHTOWN GAS on street paving for the following streets starting the week of Monday, April 10th

  • Elm Street 
  • Fayette Street
  • New Brunswick Ave
  • Maple Street
  • Smith Street
  • Hobart Street
  • State Street
  • McClellan Street (keyway)
  • Market Street
  • Brighton Avenue
  • Madison Avenue
  • First Street
  • Gordon Street

Click HERE for the information letter in English and Spanish from Z BROTHERS on UEZ Road Improvements (street paving) for the following streets starting the week of Monday, April 10th
Click HERE for the letter in English and Spanish from Z BROTHERS on UEZ Road Improvements (street paving on Hall Avenue) for the following streets starting the week of Monday, April 17th

  • Hall Avenue
  • Fayette Street

Click HERE for the Public Notice from UTITLITY SERVICE AFFLIATES AND  B&W CONSTRUCTION on the hydrant installations at the following locations starting Monday, April 10th

  • High Street
    • West corner of Center Street
    • West corner of Washington Street
    • West corner of Buckingham Street

GARBAGE AND RECYCLING SCHEDULE
Trash and recycling are picked up on the usual schedule on city construction projects unless residents are notified otherwise. The city will sometimes arrange for early pick-up to avoid interfering with work operations for the day, so residents should have all garbage and recycling to the curb the night before.

HORARIO DE BASURA Y RECICLAJE
La basura y el reciclaje se recogen en el horario habitual en los proyectos de construcción de la ciudad a menos que se notifique lo contrario a los residentes. La ciudad a veces organizará la recogida temprana para evitar interferir con las operaciones de trabajo del día, por lo que los residentes deben tener toda la basura y el reciclaje en la acera la noche anterior.